You are here: Homepage Documents test View document |
|
View documentNKS Programme Area: | NKS-R | Research Area: | Decommissioning | Report Number: | NKS-146 | Report Title: | Cost Calculations for Decommissioning and Dismantling of Nuclear Research Facilities, Phase 1 | Activity Acronym: | CostCalc | Authors: | Inga Andersson | Abstract: | Today, it is recommended that planning of decommission should form an integral part of the activities over the life cycle of a nuclear facility. However, no actual international guideline on cost calculations exists at present.
Intuitively, it might be tempting to regard costs for decommissioning of a nuclear facility as similar to those of any other plant. However, the presence of radionuclide contamination may imply that the cost is one or more orders of magnitude higher as compared to a corresponding inactive situation, the actual ratio being highly dependent on the level of contamination as well as design features and use of the facility in question. Moreover, the variations in such prerequisites are much larger than for nuclear power plants.
This implies that cost calculations cannot be performed with any accuracy or credibility without a relatively detailed consideration of the radiological and other prerequisites. Application of inadequate methodologies – especially at early stages – has often lead to large underestimations.
The goals of the project and the achievements described in the report are as follows:
1 Advice on good practice with regard to
1a Strategy and planning
1b Methodology selection
1c Radiological surveying
1d Uncertainty analysis
2 Techniques for assessment of costs
2a Cost structuring
2b Cost estimation methodologies
3 Compilation of data for plants, state of planning, organisations, e t c.
3a General descriptions of relevant features of the nuclear research facilities
3b General plant specific data
3c Example of the decommissioning of the R1 research reactor in Sweden
3d Example of the decommissioning of the DR1 research reactor in Denmark
In addition, but not described in the present report, is the establishment of a Nordic network in the area including an internet based expert system.
It should be noted that the project is planned to exist for at least three years and that the present report is an interim one covering the work for approximately the first 16 months. | Keywords: | Decommissioning; radiological survey; technical planning; methodology selection; nuclear research facility; cost calculation; early stage; cost estimation; Nordic; dismantling | Publication date: | 01 Nov 2006 | ISBN: | ISBN: 87-7893-209-2 | Number of downloads: | 7082 | Download: | NKS-146.pdf |
|
|